Shoreview's Victoria Street Rebuilds Itself Between Seasons

"My only worry is that it's going to be so popular initially that people are going to stand in the tunnel," Council Member Paul Gardner said about the new pollinator mural planned for the bike and pedestrian tunnel between the Shoreview Community Center's lower parking lot and Snail Lake. Press Publications reported the comment from the council's Aug. 3 meeting, where the design was approved.

The comment was about one tunnel. It also fits the stretch of Victoria Street N. around 4580 that holds the Community Center, City Hall, Commons Park, Haffeman Pavilion and the trail link to Snail Lake. This fall nearly every piece of that stretch is getting rebuilt, repainted or reassigned. The schedules overlap: the outdoor market ends this week, and the largest scheduled project, the county's Snail Lake trail rebuild, runs from October into December.

The calendar, end to end

Date Where What changes
Tue., Oct. 13, 3 to 6 p.m. Community Center lower lot Last outdoor Shoreview Farmers' Market of 2026
Tue., Oct. 13, 7 to 9 p.m. Shoreview Community Center Gallery 96 Art Discussion
October, per county schedule Snail Lake Regional Park, Gramsie Road to Snail Lake Road Trail rebuild scheduled to begin
Sat., Oct. 24, 3 to 5 p.m. McCullough Park, 955 County Road I Boo Bash
Tue., Nov. 10, 7 to 9 p.m. Shoreview Community Center Last Art Discussion on Gallery 96's current listing
Tue., Nov. 17, 3 to 6 p.m. Community Center upper level Indoor farmers market season opens
December, per county schedule Snail Lake Regional Park Trail work scheduled to finish
Sat., Dec. 12, 9 a.m. to noon Community Center upper level Indoor market
Early 2027 3615 Victoria St. Expected sale closing on the former fire station
Mid-to-late summer 2027 3615 Victoria St. Mi-Sant's target opening

Read top to bottom, the table shows the stretch's routine moving upstairs and indoors while the ground around it gets torn up and rebuilt. The sections below follow that order.

The market closes out a season spent beside a construction site

The Shoreview Farmers' Market has met on Tuesday afternoons in the Community Center's lower parking lot since June 2. Hours were 3 to 7 p.m. through Sept. 1, then cut back to 3 to 6 p.m. from Sept. 8 to the final outdoor date on Oct. 13.

Much of that fall stretch was spent beside a parking lot rebuild. The city's Community Center and Commons Park Improvements project scheduled work in the lower lot from Aug. 17 through mid-September. That work covered:

  • Grinding out and repaving the oldest part of the lower lot
  • A new sanitary sewer pipe from the manhole near Haffeman Pavilion to a new lift station at the lot's southeast corner
  • A retaining wall along the east side to add parking spaces
  • Curb replacement and upgraded ADA ramps

The city kept the market running in the lot through all of it and warned shoppers that it "may be on a gravel surface for several weeks." Visitors were directed to the upper lot instead.

After Oct. 13 the market moves inside to the Community Center's upper level. The indoor season runs on a monthly schedule: Tuesday, Nov. 17, from 3 to 6 p.m., then a Saturday morning date on Dec. 12 from 9 a.m. to noon. After that it returns to Tuesdays, 3 to 6 p.m., on Jan. 19, Feb. 16, March 16 and April 20, 2027. A weekly outing becomes a monthly one until spring.

Upstairs, the work continues into the fall

The lower lot was the loud part of the project. The city described a second phase starting in early fall, "with fewer anticipated impacts to community center visitors." It includes:

  1. Expanding and paving the City Hall service driveway and parking area
  2. Minor storm utility work
  3. Curb replacement and ADA upgrades in the upper lot
  4. Rehabilitating the Commons trails
  5. A new trail connection from the Commons Park trails to the Mounds Avenue playground

The city's project page doesn't say which of these are finished. The upper lot is where indoor market shoppers will park in November, and the new Mounds Avenue connection changes how the playground ties into the Commons. With no completion update posted for either one, posted signs at the upper entrance remain the most current guide.

The tunnel ties the two halves together

The tunnel runs from the Community Center's lower lot to Snail Lake, so it links the stretch that is changing this fall with the park where the county's trail work is scheduled next.

Gallery 96 Art Center chose local artists Lili Lennox and Sara Herman from 41 applicants. The two have worked together for 20 years, starting out painting theater backdrops. According to Press Publications, the design includes jack-in-the-pulpit, blue flag iris, meadow blazing star and black-eyed Susan, along with bumblebees, the American bluet damselfly and swallowtail butterflies. The project was funded by grants that Gallery 96 and the Shoreview Bikeways and Trails Committee secured from the Shoreview Community Foundation and the Ramsey-Washington County Metro Watershed District.

Some of the mural comes from residents. Gallery 96 treasurer Jeff Cooper told Press Publications that volunteers would paint their own pollinator on polytab, a sturdy fabric that sticks to the wall and becomes part of the larger piece, so people can later point to their own bee or dragonfly. The plan calls for an anti-graffiti coating and a plaque naming the sponsors, artists and volunteers once the mural is done.

The community paint event was scheduled for Aug. 13 at Haffeman Pavilion. Gallery 96's mural page also shows painting photos labeled Aug. 26, 2026. We could not find a public confirmation that the panels have been installed or the plaque mounted, so the finished tunnel is best treated as close to done.

Gallery 96 also keeps a regular schedule at the Community Center. Board members Derek Settergren and Jeff Cooper lead Art Discussions from 7 to 9 p.m. on the second Tuesday of each month. Artists bring one or two recent pieces, works in progress included, for feedback. The current listing runs through Nov. 10. That puts the Oct. 13 session on the same evening the outdoor market closes. Gallery 96's fall "Friends & Family" show hangs in the Shoreview Library Community Room.

Past the tunnel, Snail Lake's trail is scheduled to close for rebuilding

Ramsey County Parks & Recreation is running the trail project at Snail Lake Regional Park, and it is the largest item on this fall's list. The county's project page says construction "will start in October and be completed in December." The work removes and replaces the trail from Gramsie Road to Snail Lake Road, along with the Snail Lake Boulevard loop. It also adds an east-west boardwalk through the wetland to replace a section the county calls "perpetually flooded." Minnesota Legacy Parks & Trails Funds are paying for it.

The City of Shoreview's page adds that tree removal along the trail began earlier and was expected to finish by April 1, 2026. The project also includes changes to reduce flooding when water in the area rises.

As of this writing, neither agency has posted that crews are on site or which segments are closed. The county links a project extents and trail closures map on its page. Questions go to Ramsey County Parks & Recreation at 651-266-0300 or [email protected].

If the county's schedule holds, the flooded section will be replaced by a boardwalk by the end of December. Until then, the Gramsie-to-Snail Lake Road corridor is the part of this stretch most likely to be off-limits for a while.

The south end holds the next anchor

Farther south, at 3615 Victoria St., stands the empty building that was Lake Johanna Fire Department Station 140. Press Publications reported that a 2019 department needs study found growth in the area outpacing Station 140's capacity. The study recommended closing it eventually and building a replacement with room for full-time staff, larger trucks, training and future expansion.

That replacement is Station 110 at 3535 Pine Tree Drive in Arden Hills. The city listed its grand opening for July 29, 2026.

On Sept. 21, 2026, the Shoreview City Council approved selling the old station to 44 Investment company, which does business as Mi-Sant. The city's announcement says Mi-Sant plans a mini-style Vietnamese bakery and fast-casual restaurant. The menu is planned to include baguettes, croissants, breakfast sandwiches, noodle bowls, egg rolls, spring rolls and banh mi, plus coffee and bubble tea. Indoor and outdoor café seating would use the old fire truck bay, and the building would also have a group dining and meeting room. Most of the building is planned as a test kitchen for new menu items.

The deal is $1,350,000, the full asking price, and the buyer plans about $1,000,000 in improvements. Mi-Sant already has locations in Brooklyn Park and Roseville and another planned for the West End area of St. Louis Park. The city expects the sale to close in early 2027, once land use and zoning approvals are in place, and Mi-Sant is aiming to open in mid-to-late summer 2027.

The opening still depends on those approvals. If it stays on schedule, Mi-Sant would open about a year after Station 110's July 29, 2026 grand opening, and the old truck bay at 3615 Victoria would hold café tables.

If you live near the Community Center or the old Station 140 and want a clear, numbers-first read on where your home's value stands while Victoria Street changes, White Bear Lake Realty can prepare a free home valuation. It will show the comparable sales and the net proceeds math behind the number. Get a Free Home Valuation.